POSTED 02/09/2022

We were informed by the construction team that the cleanroom shut down has been delayed due to further shipping issues with the HEPA filters. We know the filters are scheduled to arrive in the United States on February 14th. However, it is uncertain how long it will take customs to clear the filters or when they will arrive at the CNF. Due to these delays the cleanroom will not be closing on Feb 14th as previously announced. We are having a planning meeting this Thursday (Feb. 10th) in order to acquire a firmer grip on the schedule. We anticipate the new date for the lab shutdown will occur the last full week in February. Thank you for your patience while we confirm plans.